Electrostatic Precipitator Outage Startup Best Practices

ESP Tech Tips

Prior to an outage, be sure to record a set of benchmark T/R readings, and particularly for a major outage, a set of V/I curves as well. Then, plan to run a set of post-outage readings, once the unit is up and running normally, for comparison.

By recording T/R readings even for short outages, you will be able to see potential areas that need attention during this outage or the next one. You may also be able to address an issue that could have caused you to reduce process production if left unattended.

The V/I curves provide a benchmark of clearance issues in the box and show which T/R’s are functioning properly versus those that need to be addressed. V/I curves will also help show the effects of other performance factors such as coal and temperature changes.

From Our Optimized Insights

Latest Insights

  • News Article

    A Message from Steve, CEO

    We want to express our appreciation for our valued customers and the dedicated team members who continue to make Neundorfer a success in our industry.

  • Case Study

    Major Steel Producer Improves ESP Performance with Neundorfer without any Shutdown Days

    A large, integrated steel producer wanted to reduce the unplanned production stops on their BOF– a result of issues with their ESP. Neundorfer provided an integrated solution that was implemented while maintaining consistent production!

  • News Article

    POS Updates & Releases

    An upcoming feature will introduce a new button to the Utilities screen, which will allow the user to generate a history snapshot file with a single click.